The Application of Mud-water Balance Method Pipe Jacking in Jinzhong Road ((Amoy Circular Road (ACR) Main Road—ACR Eastern Section)) Reconstruction Project
Abstract
In the Jinzhong Road (ACR Main Road - ACR Eastern Section) Reconstruction Project in start up area of Xiamen Cross-strait Financial Centre, mud-water balance method was adopted and successfully jacked 2.4m diameter double-hole jacking pipes for 558m. This essay demonstrates the design of pipe jacking in this project and key points of construction and management, which accrues experience for large-diameter pipe jacking under Xiamen specific geological condition in the future.
Keywords
Mud-water balance method, Pipe jacking, Jacking force, Measurement rectification
DOI
10.12783/dtetr/icmme2017/9141